Portfolio Dashboard

 

Portfolio Dashboard

SmartPM Portfolio Dashboard

SmartPM Portfolio Dashboard

Click on Highlighted Fields for Feature Insights


***Click on project name to view the Project Dashboard****
Schedule Quality Grade Planned vs. Actual Progress Historical Critical Path Delay Future Recovery End-Date Variance Schedule Compression Scheduled vs. Forecasted Completion Dates Pink Report Project- Open

Schedule Quality Grade

 

The schedule quality metric evaluates the structural integrity of you schedule and takes into factor key industry standard metrics to determine whether or not the schedule is structurally sound and feasible.

This metric is key to ensure that your project’s schedule is sufficient to manage the project. It is important to review the Schedule Quality throughout the entire project to ensure that the integrity is not compromised as the project progresses increasing the risk of delays and overruns.

 

Click to enlarge

Schedule Quality

Planned vs. Actual Progress

 

The planned vs actual progress compares the actual performance of the schedule as compared to what was planned according to the baseline.

Historical Critical Path Delay

 

Identifying Historical Critical Path and calculating is one of the most challenging calculations in all of construction and we have automated it!

This metric tells you how many days of actual critical path delay the project has suffered to date.  Behind this metric is an in depth delay analysis complete with a delay table and schedule summary that review, analyze and/or drill down on.

Click to enlarge

Critical Path

Future Recovery

 

The future recovery of a schedule captures the remediation efforts that have been put in place by the scheduler in order to recover time from the delays that have occurred thus far and bring the project completion date back in.

This is done by manipulating activity durations and logical structure of the schedule. It is very important to validate this feasibility of these changes in order to not jeopardize the future of the project.

Recovery
Audit Log           Critical Changes

End-Date Variance

 

The end date variance of a schedule captures the diversion of the current schedule completion date from the baseline schedule completion date.

If the schedule was to progress as shown in the latest schedule update, the schedule will complete this many days later than originally planned. 

Schedule Compression

 

The schedule compression captures the amount of effort remaining in the schedule as compared to the baseline.

A high schedule compression reduces the feasibility of completing the project on time, unless realistic future recovery has been put in place.

 

Scheduled vs. Forecasted Completion Dates

 

SmartPM's forecasted completion date uses a proprietary AI based algorithm based on current progress to give a realistic estimate of what the completion date of the schedule should be given things progress as they have thus far.

The scheduled completion date shows the completion date based on the current schedule update.

 

Pink Report

The Pink Report is an executive summary of the project to date that empowers you with the information you need in order to have the appropriate conversation with your leadership team or contractors. 

OAC meetings are more efficient, productive and meaningful with the Pink Report.

 

Click to View Report
Pink Report

 

Automated Forensic Delay Analysis at your fingertips. Generate the most advanced project analysis on the market - on demand.

Consultants Not Required.

Delay Analysis

Project- Open

Project Dashboard

 

Portfolio Dashboard

SmartPM Project Dashboard

SmartPM Project Dashboard

 

 

SmartPM Project Dashboard

SmartPM™ is a full-scale scheduling analytics platform.

Click the schedule link to open the schedule update in a traditional Gantt Chart view like Primavera or MS Project.

From here you can roll up your sleeves and drill down into your schedule.

Delay Audit Reports Quality Scenarios Weather Corrections Schedules Tab Back to Company Dashboard Analysis Tab Schedule Quality Critical PAth Recovery End Date Variance Compression Scheduled vs. Forecasted Back to Portfolio View

Delay

View the results of SmartPM’s automatic Historical Critical Path analysis here. The Delay Table provides you an auto generated Windows Analysis; letting you know exactly what activities were delayed, recovered, and where you stand moving forward.

Click to enlarge

Delay

Audit

Better understand the various modifications made from one schedule update to another. SmartPM™ maintains a running log of changes and dates for these changes. SmartPM™ then distills these changes to filter those changes that had a direct impact on the go-forward critical and near critical paths.

Click to enlarge

Audit

Reports

The Reports tab is your digital filing cabinet for each one of your executive level Pink Reports. From here you can customize your Pink Report for any schedule update uploaded into SmartPM™. The Pink Report is an executive summary of the project to date that empowers you with the information you need in order to have the appropriate conversations with key stakeholders, making OAC meetings more efficient, productive and meaningful.

Click to enlarge

Reports

Click to view report

View Pink Report

Quality

Review SmartPM’s analysis of your Project’s schedule quality. Here you will be able to review how well your schedules have been built, where the trouble spots are, and understand why & how they can be improved in an easy to read format.

Click to enlarge

Quality Analysis

Scenarios

Weather

Corrections

Schedules Tab

 

Click the schedule link to open the schedule update in a traditional Gantt Chart view like Primavera or MS Project.

From here you can roll up your sleeves and drill down into your schedule.

Click to Enlarge

Schedule Tab

Back to Company Dashboard

Analysis Tab

Schedule Quality

The schedule quality metric evaluates the structural integrity of you schedule and takes into factor key industry standard metrics to determine whether or not the schedule is structurally sound and feasible.

This metric is key to ensure that your project’s schedule is sufficient to manage the project. It is important to review the Schedule Quality throughout the entire project to ensure that the integrity is not compromised as the project progresses increasing the risk of delays and overruns.

Critical PAth

Identifying Historical Critical Path and calculating is one of the most challenging calculations in all of construction and we have automated it!

This metric tells you how many days of actual critical path delay the project has suffered to date.  Behind this metric is an in depth delay analysis complete with a delay table and schedule summary that review, analyze and/or drill down on.

Recovery

The future recovery of a schedule captures the remediation efforts that have been put in place by the scheduler in order to recover time from the delays that have occurred thus far and bring the project completion date back in.

This is done by manipulating activity durations and logical structure of the schedule. It is very important to validate this feasibility of these changes in order to not jeopardize the future of the project.

End Date Variance

The end date variance of a schedule captures the diversion of the current schedule completion date from the baseline schedule completion date.  If the schedule was to progress as shown in the latest schedule update, the schedule will complete this many days later than originally planned. 

Compression

The schedule compression captures the amount of effort remaining in the schedule as compared to the baseline.  A high schedule compression reduces the feasibility of completing the project on time, unless realistic future recovery has been put in place.

Scheduled vs. Forecasted

SmartPM's forecasted completion date uses a proprietary AI based algorithm based on current progress to give a realistic estimate of what the completion date of the schedule should be given things progress as they have thus far.  The scheduled completion date shows the completion date based on the current schedule update.

Back to Portfolio View