Project Dashboard

Project Dashboard

SmartPM Dashboard

SmartPM Dashboard

Click on Highlighted Fields for Feature Insights


Schedule Quality Grade Planned vs. Actual Progress Historical Critical Path Delay Future Recovery End-Date Variance Weather Days Schedule Compression Scheduled vs. Forecasted Completion Dates Project- Open

Schedule Quality Grade

 

The schedule quality metric evaluates the structural integrity of you schedule and takes into factor key industry standard metrics to determine whether or not the schedule is structurally sound and feasible.

This metric is key to ensure that your project’s schedule is sufficient to manage the project. It is important to review the Schedule Quality throughout the entire project to ensure that the integrity is not compromised as the project progresses increasing the risk of delays and overruns.

Schedule Quality Index – click image to enlarge


Planned vs. Actual Progress

 

The planned vs actual progress compares the actual performance of the schedule as compared to what was planned according to the baseline.

 

Historical Critical Path Delay

 

Identifying Historical Critical Path and calculating is one of the most challenging calculations in all of construction and we have automated it!

This metric tells you how many days of actual critical path delay the project has suffered to date.  Behind this metric is an in depth delay analysis complete with a delay table and schedule summary that review, analyze and/or drill down on.

Historical Critical Path Data- click image to enlarge


Future Recovery

 

The future recovery of a schedule captures the remediation efforts that have been put in place by the scheduler in order to recover time from the delays that have occurred thus far and bring the project completion date back in.

This is done by manipulating activity durations and logical structure of the schedule. It is very important to validate this feasibility of these changes in order to not jeopardize the future of the project.


End-Date Variance

 

The end date variance of a schedule captures the diversion of the current schedule completion date from the baseline schedule completion date.

If the schedule was to progress as shown in the latest schedule update, the schedule will complete this many days later than originally planned. 

 

Weather Days

 

The weather days metric calculates the difference between what "should have been expected" and what was then built into the baseline (based on a 10 or 30 yr average) and what actually happened on the site during the project.

SmartPM's weather metric is tied into NOAA.

This is very valuable when you are reviewing or preparing for a weather related claim.

 

Schedule Compression

 

The schedule compression captures the amount of effort remaining in the schedule as compared to the baseline.

A high schedule compression reduces the feasibility of completing the project on time, unless realistic future recovery has been put in place.

 

Scheduled vs. Forecasted Completion Dates

 

SmartPM's forecasted completion date uses a proprietary AI based algorithm based on current progress to give a realistic estimate of what the completion date of the schedule should be given things progress as they have thus far.

The scheduled completion date shows the completion date based on the current schedule update.

 

The Pink Report is an executive summary of the project to date that empowers you with the information you need in order to have the appropriate conversation with your leadership team or contractors. 

OAC meetings are more efficient, productive and meaningful with the Pink Report.

Pink Report- click images to enlarge


Automated Forensic Delay Analysis at your fingertips. Generate the most advanced project analysis on the market - on demand.

Consultants Not Required.

 

Easily provide the SmartPM system with the latest schedule updates to gain valuable insights into the progress of your project. 

With every update you will gain clarity, have the ability to predict and prepare for future outcomes and find out exactly what happened throughout your project's entire lifecycle. 

 

Project- Open

Open Project Interface- click image to enlarge