Portfolio Dashboard
Portfolio Dashboard

SmartPM Portfolio Dashboard
Schedule Quality Grade

The schedule quality metric evaluates the structural integrity of you schedule and takes into factor key industry standard metrics to determine whether or not the schedule is structurally sound and feasible.
This metric is key to ensure that your project’s schedule is sufficient to manage the project. It is important to review the Schedule Quality throughout the entire project to ensure that the integrity is not compromised as the project progresses increasing the risk of delays and overruns.
Click to enlarge
Planned vs. Actual Progress

The planned vs actual progress compares the actual performance of the schedule as compared to what was planned according to the baseline.
Historical Critical Path Delay

Identifying Historical Critical Path and calculating is one of the most challenging calculations in all of construction and we have automated it!
This metric tells you how many days of actual critical path delay the project has suffered to date. Behind this metric is an in depth delay analysis complete with a delay table and schedule summary that review, analyze and/or drill down on.
Click to enlarge
Future Recovery
The future recovery of a schedule captures the remediation efforts that have been put in place by the scheduler in order to recover time from the delays that have occurred thus far and bring the project completion date back in.
This is done by manipulating activity durations and logical structure of the schedule. It is very important to validate this feasibility of these changes in order to not jeopardize the future of the project.
End-Date Variance

The end date variance of a schedule captures the diversion of the current schedule completion date from the baseline schedule completion date.
If the schedule was to progress as shown in the latest schedule update, the schedule will complete this many days later than originally planned.
Schedule Compression

The schedule compression captures the amount of effort remaining in the schedule as compared to the baseline.
A high schedule compression reduces the feasibility of completing the project on time, unless realistic future recovery has been put in place.
Scheduled vs. Forecasted Completion Dates

SmartPM's forecasted completion date uses a proprietary AI based algorithm based on current progress to give a realistic estimate of what the completion date of the schedule should be given things progress as they have thus far.
The scheduled completion date shows the completion date based on the current schedule update.
Pink Report
The Pink Report is an executive summary of the project to date that empowers you with the information you need in order to have the appropriate conversation with your leadership team or contractors.
OAC meetings are more efficient, productive and meaningful with the Pink Report.
Automated Forensic Delay Analysis at your fingertips. Generate the most advanced project analysis on the market - on demand.
Consultants Not Required.
Project- Open
Project Dashboard
Portfolio Dashboard

SmartPM Project Dashboard
SmartPM Project Dashboard
SmartPM™ is a full-scale scheduling analytics platform.
Click the schedule link to open the schedule update in a traditional Gantt Chart view like Primavera or MS Project.
From here you can roll up your sleeves and drill down into your schedule.
Delay
Audit
Better understand the various modifications made from one schedule update to another. SmartPM™ maintains a running log of changes and dates for these changes. SmartPM™ then distills these changes to filter those changes that had a direct impact on the go-forward critical and near critical paths.
Click to enlarge
Reports
The Reports tab is your digital filing cabinet for each one of your executive level Pink Reports. From here you can customize your Pink Report for any schedule update uploaded into SmartPM™. The Pink Report is an executive summary of the project to date that empowers you with the information you need in order to have the appropriate conversations with key stakeholders, making OAC meetings more efficient, productive and meaningful.
Click to enlarge
Click to view report
Quality
Scenarios
Weather
Corrections
Schedules Tab
Back to Company Dashboard
Analysis Tab
Schedule Quality

The schedule quality metric evaluates the structural integrity of you schedule and takes into factor key industry standard metrics to determine whether or not the schedule is structurally sound and feasible.
This metric is key to ensure that your project’s schedule is sufficient to manage the project. It is important to review the Schedule Quality throughout the entire project to ensure that the integrity is not compromised as the project progresses increasing the risk of delays and overruns.
Critical PAth

Identifying Historical Critical Path and calculating is one of the most challenging calculations in all of construction and we have automated it!
This metric tells you how many days of actual critical path delay the project has suffered to date. Behind this metric is an in depth delay analysis complete with a delay table and schedule summary that review, analyze and/or drill down on.
Recovery

The future recovery of a schedule captures the remediation efforts that have been put in place by the scheduler in order to recover time from the delays that have occurred thus far and bring the project completion date back in.
This is done by manipulating activity durations and logical structure of the schedule. It is very important to validate this feasibility of these changes in order to not jeopardize the future of the project.
End Date Variance

The end date variance of a schedule captures the diversion of the current schedule completion date from the baseline schedule completion date. If the schedule was to progress as shown in the latest schedule update, the schedule will complete this many days later than originally planned.
Compression

The schedule compression captures the amount of effort remaining in the schedule as compared to the baseline. A high schedule compression reduces the feasibility of completing the project on time, unless realistic future recovery has been put in place.
Scheduled vs. Forecasted

SmartPM's forecasted completion date uses a proprietary AI based algorithm based on current progress to give a realistic estimate of what the completion date of the schedule should be given things progress as they have thus far. The scheduled completion date shows the completion date based on the current schedule update.