Portfolio Dashboard

 

Portfolio Dashboard

SmartPM Portfolio Dashboard

SmartPM Portfolio Dashboard

Click on Highlighted Fields for Feature Insights


***Click on project name to view the Project Dashboard****
Schedule Quality Grade Planned vs. Actual Progress Historical Critical Path Delay Future Recovery End-Date Variance Schedule Compression Scheduled vs. Forecasted Completion Dates Project- Open

Schedule Quality Grade

 

The schedule quality metric evaluates the structural integrity of you schedule and takes into factor key industry standard metrics to determine whether or not the schedule is structurally sound and feasible.

This metric is key to ensure that your project’s schedule is sufficient to manage the project. It is important to review the Schedule Quality throughout the entire project to ensure that the integrity is not compromised as the project progresses increasing the risk of delays and overruns.

Schedule Quality Index – click image to enlarge


Planned vs. Actual Progress

 

The planned vs actual progress compares the actual performance of the schedule as compared to what was planned according to the baseline.

Historical Critical Path Delay

 

Identifying Historical Critical Path and calculating is one of the most challenging calculations in all of construction and we have automated it!

This metric tells you how many days of actual critical path delay the project has suffered to date.  Behind this metric is an in depth delay analysis complete with a delay table and schedule summary that review, analyze and/or drill down on.

Historical Critical Path Data- click image to enlarge


Future Recovery

 

The future recovery of a schedule captures the remediation efforts that have been put in place by the scheduler in order to recover time from the delays that have occurred thus far and bring the project completion date back in.

This is done by manipulating activity durations and logical structure of the schedule. It is very important to validate this feasibility of these changes in order to not jeopardize the future of the project.

Recovery- Delay Tables- click images to enlarge


End-Date Variance

 

The end date variance of a schedule captures the diversion of the current schedule completion date from the baseline schedule completion date.

If the schedule was to progress as shown in the latest schedule update, the schedule will complete this many days later than originally planned. 

Schedule Compression

 

The schedule compression captures the amount of effort remaining in the schedule as compared to the baseline.

A high schedule compression reduces the feasibility of completing the project on time, unless realistic future recovery has been put in place.

 

Scheduled vs. Forecasted Completion Dates

 

SmartPM's forecasted completion date uses a proprietary AI based algorithm based on current progress to give a realistic estimate of what the completion date of the schedule should be given things progress as they have thus far.

The scheduled completion date shows the completion date based on the current schedule update.

 

The Pink Report is an executive summary of the project to date that empowers you with the information you need in order to have the appropriate conversation with your leadership team or contractors. 

OAC meetings are more efficient, productive and meaningful with the Pink Report.

Pink Report- click images to enlarge


Automated Forensic Delay Analysis at your fingertips. Generate the most advanced project analysis on the market - on demand.

Consultants Not Required.

 

Project- Open

Project Dashboard

Project Dashboard

SmartPM™ is a full-scale scheduling analytics platform.
Click the schedule link to open the schedule update in a traditional Gantt Chart view like Primavera or MS Project. From here you can roll up your sleeves and drill down into your schedule.

Project Schedule

Run Delay Analysis

Upload New Schedule

Create Scenario

Analysis

Scenarios

Weather

Corrections

Back to Company Dashboard

Schedule Quality

Critical Path

Recovery

End Date Variance

Compression

Scheduled v Forecasted

Back to Portfolio View

Project Schedule

Project Metrics & Gantt View


SmartPM™ is a full-scale scheduling analytics platform. Click the schedule link to open the schedule update in a traditional Gantt Chart view like Primavera or MS Project. From here you can roll up your sleeves and drill down into your schedule.

Run Delay Analysis

Run Delay Analysis


Run Delay Analysis: Identifying historical critical path delays that drove project cost & schedule has now been completely automated! Click the Run Delay Analysis button to kick off a Historical Critical Path analysis that will finish in just minutes.

Upload New Schedule

Upload New Schedule


Upload New Schedule: SmartPM™ analyzes ALL of your project’s schedule updates to produce the true story of your job. Uploading schedule updates is as easy as creating an e-mail attachment. Just select the Primavera or Microsoft Project file right off your computer or online file sharing service

Create Scenario

Create Scenario Info

Analysis

Scenarios

Weather

Corrections

Back to Company Dashboard

Schedule Quality

The schedule quality metric evaluates the structural integrity of you schedule and takes into factor key industry standard metrics to determine whether or not the schedule is structurally sound and feasible.

This metric is key to ensure that your project’s schedule is sufficient to manage the project. It is important to review the Schedule Quality throughout the entire project to ensure that the integrity is not compromised as the project progresses increasing the risk of delays and overruns.


Schedule Quality Index – click image to enlarge


Critical Path

Identifying Historical Critical Path and calculating is one of the most challenging calculations in all of construction and we have automated it!

This metric tells you how many days of actual critical path delay the project has suffered to date.  Behind this metric is an in depth delay analysis complete with a delay table and schedule summary that review, analyze and/or drill down on.

Historical Critical Path Data- click image to enlarge


Recovery

The future recovery of a schedule captures the remediation efforts that have been put in place by the scheduler in order to recover time from the delays that have occurred thus far and bring the project completion date back in.

This is done by manipulating activity durations and logical structure of the schedule. It is very important to validate this feasibility of these changes in order to not jeopardize the future of the project.


Recovery- Delay Tables- click images to enlarge


End Date Variance

The end date variance of a schedule captures the diversion of the current schedule completion date from the baseline schedule completion date.  If the schedule was to progress as shown in the latest schedule update, the schedule will complete this many days later than originally planned. 

Compression

The schedule compression captures the amount of effort remaining in the schedule as compared to the baseline.  A high schedule compression reduces the feasibility of completing the project on time, unless realistic future recovery has been put in place. 

 

Scheduled v Forecasted

SmartPM's forecasted completion date uses a proprietary AI based algorithm based on current progress to give a realistic estimate of what the completion date of the schedule should be given things progress as they have thus far.  The scheduled completion date shows the completion date based on the current schedule update

Back to Portfolio View

Project Dashboard

Project Dashboard

SmartPM™ is a full-scale scheduling analytics platform.
Click the schedule link to open the schedule update in a traditional Gantt Chart view like Primavera or MS Project. From here you can roll up your sleeves and drill down into your schedule.

Project Schedule

Run Delay Analysis

Upload New Schedule

Create Scenario

Analysis

Scenarios

Weather

Corrections

Back to Company Dashboard

Schedule Quality

Critical Path

Recovery

End Date Variance

Compression

Scheduled v Forecasted

Back to Portfolio View

Project Schedule

Project Metrics & Gantt View


SmartPM™ is a full-scale scheduling analytics platform. Click the schedule link to open the schedule update in a traditional Gantt Chart view like Primavera or MS Project. From here you can roll up your sleeves and drill down into your schedule.

Run Delay Analysis

Run Delay Analysis


Run Delay Analysis: Identifying historical critical path delays that drove project cost & schedule has now been completely automated! Click the Run Delay Analysis button to kick off a Historical Critical Path analysis that will finish in just minutes.

Upload New Schedule

Upload New Schedule


Upload New Schedule: SmartPM™ analyzes ALL of your project’s schedule updates to produce the true story of your job. Uploading schedule updates is as easy as creating an e-mail attachment. Just select the Primavera or Microsoft Project file right off your computer or online file sharing service

Create Scenario

Create Scenario Info

Analysis

Scenarios

Weather

Corrections

Back to Company Dashboard

Schedule Quality

The schedule quality metric evaluates the structural integrity of you schedule and takes into factor key industry standard metrics to determine whether or not the schedule is structurally sound and feasible.

This metric is key to ensure that your project’s schedule is sufficient to manage the project. It is important to review the Schedule Quality throughout the entire project to ensure that the integrity is not compromised as the project progresses increasing the risk of delays and overruns.


Schedule Quality Index – click image to enlarge


Critical Path

Identifying Historical Critical Path and calculating is one of the most challenging calculations in all of construction and we have automated it!

This metric tells you how many days of actual critical path delay the project has suffered to date.  Behind this metric is an in depth delay analysis complete with a delay table and schedule summary that review, analyze and/or drill down on.

Historical Critical Path Data- click image to enlarge


Recovery

The future recovery of a schedule captures the remediation efforts that have been put in place by the scheduler in order to recover time from the delays that have occurred thus far and bring the project completion date back in.

This is done by manipulating activity durations and logical structure of the schedule. It is very important to validate this feasibility of these changes in order to not jeopardize the future of the project.


Recovery- Delay Tables- click images to enlarge


End Date Variance

The end date variance of a schedule captures the diversion of the current schedule completion date from the baseline schedule completion date.  If the schedule was to progress as shown in the latest schedule update, the schedule will complete this many days later than originally planned. 

Compression

The schedule compression captures the amount of effort remaining in the schedule as compared to the baseline.  A high schedule compression reduces the feasibility of completing the project on time, unless realistic future recovery has been put in place. 

 

Scheduled v Forecasted

SmartPM's forecasted completion date uses a proprietary AI based algorithm based on current progress to give a realistic estimate of what the completion date of the schedule should be given things progress as they have thus far.  The scheduled completion date shows the completion date based on the current schedule update

Back to Portfolio View

The Power of Construction Schedule Data

Unlock the True Power

An alarming 75% of commercial construction projects are delayed and/or over budget. One major reason for this problem is mismanagement of construction schedules. A successful construction project must begin with a well-conceived, executable schedule.  All the information required to determine the success or failure of a project is contained within the schedule.

The problem is there has never been a simple, cost-effective, or reliable way to analyze construction schedules.

Until now.